Sorry for the long time between posts - we've been out of town a lot but the work has not stopped!
Roof and porch were completed (except for metal which comes later), inside framing completed, the A/C guys are running ductwork, plumbers come next week for rough in and electrical begins. We have already installed the porch lights and hope to run wire next week - then the framers can close in the ceiling of the porch. Our windows were delayed but should also come in next week - once installed the framers will start the exterior. Since the weather is getting warmer the mason guys will be back to work on our stone. It's a little crazy around here :)
Side view standing at the Maloney's (neighbor). All of the columns are finished. |
Todd taking a break from cleaning. Great picture of the front columns . |
Looking into our main living space! |
Looking back toward the 2nd level. |
Todd's mechanical room - electrical panels installed. |
Mechanical room again - A/C unit and radiantec controls. |
A/C ductwork in basement. |
Just a picture of the porch outside of our bedroom - our morning coffee area!! |
Lighting! |
Exterior electrical boxes - electric company should run power next week. |
We HAD to take a picture with the jeep :) |